post-template-default,single,single-post,postid-700,single-format-standard,bridge-core-2.6.8,qode-page-transition-enabled,ajax_fade,page_not_loaded,,qode_grid_1300,footer_responsive_adv,hide_top_bar_on_mobile_header,qode-content-sidebar-responsive,qode-child-theme-ver-1.0.0,qode-theme-ver-25.3,qode-theme-bridge,disabled_footer_bottom,qode_header_in_grid,wpb-js-composer js-comp-ver-6.6.0,vc_responsive,elementor-default,elementor-kit-345
 

MidAmerican Energy Company

MidAmerican Energy Company

MVP 3 and 4 345kV/161kV Transmission Project

Installed 121 miles of double circuit 345kV / 161kV self-weathering steel monopoles including removal of existing 161kV in existing ROW. Installed / Expanded three 345kV Substations including O’Brien, Kossuth, and Webster. Installed 71 miles of MVP 4 transmission line of DC345/ 161kV self-weathering steel monopoles, including removal of existing 161kV transmission line in existing ROW. Includes one 345kV Black Hawk Substation Expansion. Read more