post-template-default,single,single-post,postid-700,single-format-standard,bridge-core-2.6.8,qode-page-transition-enabled,ajax_fade,page_not_loaded,,qode_grid_1300,footer_responsive_adv,hide_top_bar_on_mobile_header,qode-content-sidebar-responsive,qode-child-theme-ver-1.0.0,qode-theme-ver-25.3,qode-theme-bridge,disabled_footer_bottom,qode_header_in_grid,wpb-js-composer js-comp-ver-7.9,vc_responsive,elementor-default,elementor-kit-345
 

MidAmerican Energy Company

MidAmerican Energy Company

MVP 3 and 4 345kV/161kV Transmission Project

Installed 121 miles of double circuit 345kV / 161kV self-weathering steel monopoles including removal of existing 161kV in existing ROW. Installed / Expanded three 345kV Substations including O’Brien, Kossuth, and Webster. Installed 71 miles of MVP 4 transmission line of DC345/ 161kV self-weathering steel monopoles, including removal of existing 161kV transmission line in existing ROW. Includes one 345kV Black Hawk Substation Expansion. Read more

No Comments

Sorry, the comment form is closed at this time.